Tulip Grove Renovation More Than Two Years Behind Schedule

by Lori Morrow

IMG_8106 (1)June 20th , 2016 was my daughter’s last day at Tulip Grove Elementary School, and it was a bittersweet farewell. Tulip Grove students and staff were originally scheduled to return to a newly renovated building this summer. However, the Tulip Grove community is still waiting for construction to begin, though state funding was approved two years ago.

September 2012: The updated Parsons Report (or Facility Conditions Assessment) identified Tulip Grove Elementary School as one of three schools with a Facility Condition Index value greater than 75%, indicating the need for major repairs and renovation. (The Facility Condition Index is the ratio of the cost of repairs to the cost of replacement.) Tulip Grove had previously been identified as one of nine schools recommended for replacement in the May 2008 Facility Condition Assessment Study.

2011-2013: Meetings about educational specifications and designs took place over this two-year period. Ultimately plans for a major renovation and addition were approved, adding approximately 15,000 sq. ft to the current facility to meet newer school standards while maintaining the State Rated Capacity of 411 students.

October 2012: Funding Request was submitted for FY2014 funds

November 2013: Presentation slides from GWWO Architects, Inc. listed the following timeline:

  • Design Development (DD) Submission: Oct. 11, 2013
  • Construction Document (CD) Phase: October 2013-February 2014
  • Permit Submission: March 2014
  • Bid Phase: April 2014-June 2014
  • Construction: July 2014-December 2015

December 2013: Parents were invited to a preliminary community meeting with the PGCPS Capital Improvement Program (CIP) team to discuss swing space where children would be housed during the construction period. Initial options of transporting children to vacant PGCPS facilities at Berkshire Elementary or Middleton Valley Elementary were not received well as these schools are 19-21 miles from Tulip Grove Elementary School.

February 2014: The CIP Team returned for a second community meeting to discuss swing space. Most community members expressed a desire to find a location in the greater Bowie area. (Meeting summarized in City of Bowie memorandum)

March 2014: Swing space was still undecided although parents had been actively engaging with the PGCPS Board of Education since the February meeting. (See this story in the Gazette, and this story in the Capital Gazette Bowie Blade, both from March 2014.)

April 2, 2014: The Parent Teacher Association (PTA) President was notified that Prince George’s County would allow Tulip Grove to use the Meadowbrook facility, which had been the site of an elementary school that closed in 1981, as swing space.

June – August 2014: The Meadowbrook facility was renovated and prepared for use as a school again.

August 2014: Students began the 2014-15 school year at “Tulip Grove @Meadowbrook”. Because the school site was across a major road from the school boundary area, all Tulip Grove students are now eligible for bus transportation, increasing the number of bus routes from two to seven.

Fall 2014-Winter 2015: There was minimal communication from the CIP Team to the PTA regarding construction updates. Neighbors around Tulip Grove could see that little had changed at the old school site. Per the timelines provided by PGCPS staff, the project was behind schedule before students began the 2014-15 school year, but that information was not communicated to parents.

Continue reading